Project Overview
Sad but true, the University of Utah Medical Plaza Towers that have been standing tall since 1971 are coming down for good. The Medical Towers and adjoining townhouses are long past their use-by date and the university has struggled to maintain these outdated facilities in recent years. The U Facilities Project, Design & Construction project management team is launching the abatement and demolition project of the aged buildings.
Project Timeline
October 2023 – Construction project crews begin abatement of buildings
Summer 2024 – The abatement phase concludes and demolition teams mobilize
Spring 2024 – Demolition concludes and the project team fills and grades the project site
What to Expect
- The project site has been blocked off with safety construction fencing
- Expect dump trucks driving in and out of the area as they remove waste materials
- Construction project hours are 8:00 am – 5:00 pm